Completed Access to Information Requests

About this information

Search the summaries of completed Access to Information (ATI) requests to find information about ATI requests made to the Government of Canada after January 2020. If you find a summary of interest, you can request a copy of the records at no cost using the form below each summary. Requests made through this form are considered informal requests and are not subject to the same requirements as requests under the Access to Information Act (ATIA).

If you don’t find what you are looking for you can request additional government records under an institution’s control by contacting the institution’s Access to Information and Privacy Coordinator or by submitting a formal access to information request.

*All information provided will incorporate the necessary exemptions and exclusions as per the Access to Information Act and the Privacy Act.

Download datasets of the summaries of completed access to information requests.

Current Search

Report Type

Organization

Disposition

Year

Month

Found 21 record(s)

Req # A 2020_0001

Provide copies of any and all communication and information records produced between May 1, 2018, and March 6, 2020 regarding the potential of the federal governments selling equity in TMP, TMEP, and related government-owned assets, and any related considerations and analysis. This includes any and all letters or e-mails between employees and/or board members of CDIC (including employees and board members of the CDIC subsidiary Trans Mountain Corporation) and the Department of Finance or the office of the Minister of Finance. This also includes memos, briefing materials, background documents, research and analysis, powerpoint presentations, or any other written materials produced for internal consideration at CDIC or for review by officials at the Department of Finance or the office of the Minister of Finance.

Organization: Canada Development Investment Corporation

261 page(s)
February 2021

Req # A 2020_0008

The letter from Trans Mountain to CDEV referred to in the June 2019 minutes in screen shot [Letter from TMC to Minister of Finance and CDEV].

Organization: Canada Development Investment Corporation

2 page(s)
February 2021

Req # A-2020-00035

Minimum Complement Procedure Procedure: All versions of the approved Minimum Complement Procedure applicable to all Canadian Nuclear Power Plants, including Gentilly II, PNGS A, PNGS B, and PNGS A and d B Systems (Unit 0).

Organization: Canadian Nuclear Safety Commission

170 page(s)
February 2021

Req # A-2020-00138

Provide a list of action items produced by the CNSC’s Executive Committee in October 2020. Please also provide any briefing materials including and not limited to: briefing notes, information notes, scenario notes; anything that the Executive Committee has been briefed on in October 2020. Also include meeting minutes or agendas.

Organization: Canadian Nuclear Safety Commission

182 page(s)
February 2021

Req # A-2020-00153

A Record of Decision states the following: “A Hydro-Quebec representative explained that a waste management strategy was forwarded to CNSC staff in 2010, and this strategy was recently revised to adapt to the new situation leading to decommissioning. The revised strategy was submitted to the CNSC staff in March 2016.” Please provide a copy of the aforementioned waste management strategies submitted by Hydro Quebec in 2010 and 2016.

Organization: Canadian Nuclear Safety Commission

0 page(s)
February 2021

Req # A-2020-00157

Please provide all documents related to the CANDU Senior Regulators Group meeting which took place in November 2019.

Organization: Canadian Nuclear Safety Commission

278 page(s)
February 2021

Req # A-2020-00158

Please provide all briefing, scenario and information notes produced and/or provided to the CNSC president as well as Vice President Ramzi Jammal in November 2020.

Organization: Canadian Nuclear Safety Commission

312 page(s)
February 2021

Req # A-2020-00159

Provide all CNSC produced documents or official correspondence (internal or external related to the CNSC expectations for OPG’s proposal to (again) extend the life of the Pickering nuclear station past its currently approved operating life. The media began mention OPG was considering this in January 2020.

Organization: Canadian Nuclear Safety Commission

3 page(s)
February 2021

Req # A-2020-00163

Provide all deliverables provided by 1776464 Ontario Ltd, which was for a research project on probabilistic assessments in 2019.

Organization: Canadian Nuclear Safety Commission

109 page(s)
February 2021

Req # A-2020-00169

Provide a list of action items produced by the CNSC’s Executive Committee in November 2020. Please also provide any briefing materials including and not limited to: briefing notes, information notes, scenario notes; anything that the Executive Committee has been briefed on in November 2020. Also include meeting minutes or agendas.

Organization: Canadian Nuclear Safety Commission

116 page(s)
February 2021
Date modified: